Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : NORTHERN REGION SYSTEM STRENGHTENING SCHEME-XII.

Reported Date : 17-JAN-11

Monthly Report : 11 / 2010

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
261.550261.55

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
127.7413.462.16143.36

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20100/09/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
44.6526.78

Ministry Review Date

LatestLastPhysical Progress (%)Status
15-NOV-10100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks