Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : BONGAIGAON THERMAL POWER PROJECT.

Reported Date : 13-JUN-19

MOU Status : Project Under MOU for 2016-2017

Monthly Report : 4 / 2019

Cost Overrun (%)-   86.27

Time Overrun (Months)-    89

Total/Pending/Completed Milestone - 38 / 0 / 38

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
4375.3581508150

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
7457.41007000

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20113/20193/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
346.54393.8

Ministry Review Date

LatestLastPhysical Progress (%)Status
04-SEP-180Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone