Project Summary
Project Summary
Sector Name : POWER.
Agency Name : THDC INDIA LIMITED.
Project Name : VISHNUGAD PIPALKOTI HYDRO ELECTRIC PROJECT.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 32 / 19 / 13

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2491.583860.356823.72

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4700.24118.9599.274918.46

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20130/03/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1254.790

Ministry Review Date

LatestLastPhysical Progress (%)Status
03-JUN-2571Ongoing

Monthly Status

Background Information

• Dam excavation around 97% completed. Dam concreting in all five blocks is in progress. • Heading and benching of all 3 DCs completed and around 81% concrete lining completed, and balance is in progress. • HRT construction by TBM has been completed in 6060 m out of 11150 m and is in progress and targeted by Apr’26. • In HRT by DBM (total scope: 1800 m), 81 % excavation completed. Overt lining completed in 975 m. • Machine Hall: In Unit-1, erection of Spiral casing is in progress. Assembly work of Rotor of Unit-1 and Stay ring of Unit-2 is also in progress in Service Bay. In Unit-2, concreting up to Stay ring pedestal foundation is in progress. In Unit-3 & 4, concreting of U/s crane beam columns is in progress. • Transformer Hall: Unit-1 handed over to EM for EoT erection work. In Unit-2, preparatory work for GIS slab casting is in progress and casting of balance GIS slab columns in other units is in progress. • In TRT, around 89.2% heading and 22.5 % benching excavation completed, and balance is in progress. Overt lining completed in around 529 m and balance is in progress. • EM Supplies: 64% Equipment materials have been completed. •River Diversion and Upstream Coffer Dam: Completed •Dam excavation around 82.30% completed. Dam Concreting of Block -1 (NOF) Left Bank is in Progress. •Heading of all 3 DCs completed, benching is in progress and an overall around 97% excavation and 59.42% concrete lining completed. •Mining of entry adit to HRT through TBM has been completed. HRT construction by TBM has been completed in around 1057 m length. TBM encountered setbacks due to seepage, a stuck conveyor belt and damage to the mechanical seal, leading to a halt in TBM operations from 01.03.2024 to 25.03.2024. Consequently, only 30 m of HRT could be constructed in March 2024. After resolving these issues with technical experts, TBM operations resumed on 26.03.2024 and are currently ongoing. •In Transformer Hall: Excavation and support measures has been completed. •In Machine Hall: In Service Bay, for EoT erection rail sole plates at both U/S and D/S side placed. The Girder of both EOT cranes is erected on the beam. EoT erection is targeted by end of Apr’24. In Unit area, benching is in progress and Unit-1 pit excavation is targeted by end of Apr’24 •In TRT, 62.20% heading excavation completed and balance is in progress. •At TRT outlet area, slope stabilization work is completed. •EM Supplies: 48% Equipment/ materials have been completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks