Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NORTH EAST ELECTRIC POWER CORPORATION.
Project Name : PARE HYDRO ELECTRIC PROJECT.

Reported Date : 20-JUL-18

Monthly Report : 5 / 2018

  

   

Total/Pending/Completed Milestone - 38 / 0 / 38

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
573.991337.761337.76

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1621.1712.064.371637.6

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20134/20185/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
56.810

Ministry Review Date

LatestLastPhysical Progress (%)Status
20-APR-18100Completed

Monthly Status

Background Information

COD for Unit-I & II declared on 28.05.18 and 21.05.18 respectively.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks