Reported Date :
17-SEP-15
|
MOU Status :
Not Under MOU for 2015-2016
|
Monthly Report :
8
/
2015
|
Cost Overrun (%)- 47.83
|
Time Overrun (Months)-
17
|
Total/Pending/Completed Milestone -
20
/
0
/
20
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |