Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : BARH STPP STAGE -II.

Reported Date : 17-SEP-15

MOU Status : Not Under MOU for 2015-2016

Monthly Report : 8 / 2015

Cost Overrun (%)-   47.83

Time Overrun (Months)-    17

Total/Pending/Completed Milestone - 20 / 0 / 20

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
7341.0410852.4610852.46

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
884012208962

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20130/03/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
01027

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone