Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : MOUDA STPP.

Reported Date : 08-AUG-14

MOU Status :

Monthly Report : 6 / 2014

Cost Overrun (%)-   10.1

Time Overrun (Months)-    19

Total/Pending/Completed Milestone - 16 / 0 / 16

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
5459.2806010.89

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4056004056

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20120/03/2014

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
01277

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone