Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TRANSMISSION SYSTEM ASSOCIATED WITH KORBA III GENERATION PROJECT.

Reported Date : 08-AUG-11

MOU Status :

Monthly Report : 6 / 2011

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
276.610276.61

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
197.09.151.92199.16

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20110/06/2011

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
10.80

Ministry Review Date

LatestLastPhysical Progress (%)Status
15-NOV-10100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone