Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : SUPPLIMENTARY TRANSMISSION ASSOCIATED WITH DVC AND MAITHON RBC.

Reported Date : 18-FEB-15

Monthly Report : 12 / 2014

  

   

Total/Pending/Completed Milestone - 6 / 0 / 6

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2360.952580.92580.9

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2117.1128.74.32150.11

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20120/012/2014

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
4.50

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks