Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : NORTH- EAST NORTH WESTERN INTERCONNECTOR I PROJECT.

Reported Date : 10-MAY-22

Monthly Report : 4 / 2022

  

   

Total/Pending/Completed Milestone - 26 / 3 / 23

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
11130.19013199

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
12394.950012394.95

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20130/03/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks