Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : SYSTEM STRENGHTENING -XI IN SOUTHERN REGION.

Reported Date : 10-OCT-12

Monthly Report : 8 / 2012

  

   

Total/Pending/Completed Milestone - 5 / 0 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
196.10196.1

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
132.53.982.62139.1

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20110/08/2012

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
19.40

Ministry Review Date

LatestLastPhysical Progress (%)Status
15-NOV-10100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks