Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : 765 KV SYSTEM FOR CENTRAL PART OF NORTHERN GRID PART-I.

Reported Date : 19-JUL-13

Monthly Report : 5 / 2013

  

   

Total/Pending/Completed Milestone - 4 / 0 / 4

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1347.3201347.32

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1205.60.51206.1

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20120/05/2013

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
62.740

Ministry Review Date

LatestLastPhysical Progress (%)Status
15-NOV-10100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks