Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : 765 KV SYSTEM FOR CENTRAL PART OF NORTHERN GRID PART-I.

Reported Date : 19-JUL-13

MOU Status :

Monthly Report : 5 / 2013

Cost Overrun (%)-   0

Time Overrun (Months)-    15

Total/Pending/Completed Milestone - 4 / 0 / 4

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1347.3201347.32

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1205.60.51206.1

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20120/05/2013

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
62.740

Ministry Review Date

LatestLastPhysical Progress (%)Status
15-NOV-10100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone