Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : 765 KV POOLING STATION AND NETWORK WITH DVC AND MAITHOB RBC.

Reported Date : 06-FEB-15

Monthly Report : 12 / 2014

  

   

Total/Pending/Completed Milestone - 11 / 0 / 11

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
7075.3307075.33

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
6322.5685.65.86413.96

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20120/012/2014

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
132.90

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks