Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NORTH EAST ELECTRIC POWER CORPORATION.
Project Name : TRIPURA GAS BASED POWER PROJECT.

Reported Date : 13-JUN-19

MOU Status : Not Under MOU for 2016-2017

Monthly Report : 4 / 2019

Cost Overrun (%)-   156.12

Time Overrun (Months)-    69

Total/Pending/Completed Milestone - 26 / 0 / 26

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
421.0101078.31

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
963.2300963.23

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20130/04/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone