Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : RIHAND STTP STAGE-III (2X500MW).

Reported Date : 08-AUG-14

MOU Status :

Monthly Report : 6 / 2014

Cost Overrun (%)-   0

Time Overrun (Months)-    17

Total/Pending/Completed Milestone - 16 / 0 / 16

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
6230.8106230.81

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4357004357

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20120/03/2014

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
0702

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone