Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TRANSMISSION SYSTEM OF VINDHUACHAL -IV AND RIHAND -III GEN. PROJ..

Reported Date : 01-OCT-15

Monthly Report : 8 / 2015

  

   

Total/Pending/Completed Milestone - 13 / 5 / 8

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
4672.9904672.99

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3680.9788.603769.57

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20120/08/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
163.40

Ministry Review Date

LatestLastPhysical Progress (%)Status
23-SEP-14100Completed

Monthly Status

Background Information

Project completed & commissioned.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks