Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : 765KV SYSTEM FOR CENTRAL PART OF NORTHERN REGION GRID - PART-III.

Reported Date : 05-MAR-14

MOU Status :

Monthly Report : 1 / 2014

Cost Overrun (%)-   0

Time Overrun (Months)-    19

Total/Pending/Completed Milestone - 8 / 0 / 8

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1075.1201075.12

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
813.824.4500

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20120/012/2013

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone