Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TRANSMISSION SYSTEM ASSOCIATED WITH PALLATANA GBPP and BPTS..

Reported Date : 07-FEB-19

Monthly Report : 12 / 2018

  

   

Total/Pending/Completed Milestone - 23 / 5 / 18

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
21442932.882932.88

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2631.3638.602669.96

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20126/20180/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
138.30

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks