Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TRANSMISSION SYSTEM ASSOCIATED WITH PALLATANA GBPP and BPTS..

Reported Date : 07-FEB-19

MOU Status : Not Under MOU for 2016-2017

Monthly Report : 12 / 2018

Cost Overrun (%)-   36.79

Time Overrun (Months)-    N.A.

Total/Pending/Completed Milestone - 23 / 5 / 18

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
21442932.882932.88

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2631.3638.602669.96

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20126/20180/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
138.30

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone