Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : IMMEDIATE EVACUATION SYSTEM FOR NABINAGAR TPS.

Reported Date : 06-AUG-12

Monthly Report : 6 / 2012

  

   

Total/Pending/Completed Milestone - 9 / 0 / 9

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
215.860215.86

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
179.30.4179.7

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20120/06/2012

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
8.10

Ministry Review Date

LatestLastPhysical Progress (%)Status
15-NOV-10100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks