Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TRANSMISSION SYSTEM FOR PHASE-I GEN PROJECT IN ORISSA - PART-A.

Reported Date : 07-MAR-16

Monthly Report : 1 / 2016

  

   

Total/Pending/Completed Milestone - 11 / 0 / 11

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2074.862348.372348.37

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1823.24152.701975.94

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20136/20151/2016

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
78.10

Ministry Review Date

LatestLastPhysical Progress (%)Status
23-SEP-14100Completed

Monthly Status

Background Information

Project completed. 765KV S/C Angul - Jharsaguda line complete ICT-IV at 765/400KV Angul S/stn. complete

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks