Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : INTERCONNECTION BETWEEN ELECTTRICAL GRIDS OF INDIA AND BANGLADESH -INDIAN PORTION.

Reported Date : 14-OCT-13

MOU Status :

Monthly Report : 8 / 2013

Cost Overrun (%)-   0

Time Overrun (Months)-    10

Total/Pending/Completed Milestone - 14 / 0 / 14

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
160.320160.32

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
7212.662.9787.63

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20120/08/2013

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
20.580

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone