Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TRANSMISSION SYSTEM ASSOCIATED WITH KRISHNAPATNAM-PART-A.

Reported Date : 01-MAY-13

MOU Status :

Monthly Report : 3 / 2013

Cost Overrun (%)-   0

Time Overrun (Months)-    -5

Total/Pending/Completed Milestone - 14 / 0 / 14

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
779.210779.21

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
358.2383.315756.5

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20130/03/2013

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
517.6322.6

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone