Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : NORTHERN REGION SYSTEM STRENGHENING SCHEME XVI.

Reported Date : 07-SEP-17

Monthly Report : 7 / 2017

  

   

Total/Pending/Completed Milestone - 9 / 0 / 9

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
752.64757.94757.94

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
614.9218.70633.62

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20136/20177/2017

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
15.830

Ministry Review Date

LatestLastPhysical Progress (%)Status
10-AUG-18100Completed

Monthly Status

Background Information

Project completed & commissioned.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks