Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : NORTHERN REGION SYSTEM STRENGTHENING SCHEME-XXI.

Reported Date : 08-SEP-16

Monthly Report : 7 / 2016

  

   

Total/Pending/Completed Milestone - 11 / 1 / 10

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1677.5701677.57

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1475.221201487.22

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20130/06/2016

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
10

Ministry Review Date

LatestLastPhysical Progress (%)Status
22-FEB-16100Completed

Monthly Status

Background Information

Project completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks