Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TRANSMISSION SYSTEM FOR PHASE-I GEN.PROJ.IN ORISSA PART-C.

Reported Date : 01-OCT-15

MOU Status : Not Under MOU for 2015-2016

Monthly Report : 8 / 2015

Cost Overrun (%)-   20.87

Time Overrun (Months)-    17

Total/Pending/Completed Milestone - 13 / 3 / 10

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2569.253105.513105.51

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2767.47109.102876.57

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20146/20158/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
72.50

Ministry Review Date

LatestLastPhysical Progress (%)Status
23-SEP-14100Completed

Monthly Status

Background Information

Project completed & commissioned. 765KV S/C Gwalior - jaipur line Ckt-II completed 765KV S/C Jaipur - Bhiwani line completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone