Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : ESTABLISHMENT OF POOLING STATIONS AT CHAMPA AND RAIGARH FOR IPP GENERATION PROJECT IN CHHATTISGARH.

Reported Date : 18-JUL-17

MOU Status : Not Under MOU for 2016-2017

Monthly Report : 4 / 2017

Cost Overrun (%)-   17.77

Time Overrun (Months)-    31

Total/Pending/Completed Milestone - 12 / 0 / 12

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1961.872310.582310.58

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1817.05001817.05

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/201412/201612/2016

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
600

Ministry Review Date

LatestLastPhysical Progress (%)Status
23-MAR-170Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone