Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TRANSMISSION SYSTEM FOR IPP GENERATION PROJECTS IN MP AND CHATTISGARH.

Reported Date : 06-AUG-15

MOU Status : Not Under MOU for 2015-2016

Monthly Report : 6 / 2015

Cost Overrun (%)-   17.57

Time Overrun (Months)-    18

Total/Pending/Completed Milestone - 12 / 3 / 9

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1366.341606.381606.38

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1294.6626.301320.96

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20134/20156/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
86.40

Ministry Review Date

LatestLastPhysical Progress (%)Status
23-SEP-14100Completed

Monthly Status

Background Information

Project completed. 765/400KV Vadodra sub station (GIS) completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone