Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : SYTEM STRENGTHENING XIII OF SR GRID.

Reported Date : 01-OCT-21

Monthly Report : 9 / 2021

  

   

Total/Pending/Completed Milestone - 12 / 2 / 10

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
487.490639.46

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
590.300590.3

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20140/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks