Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TRANSMISSION SYSTEM STRENGTHENING IN WESTERN PART OF WR FOR IPPS GENERATION PROJECTS IN CHATTISGARH.

Reported Date : 07-NOV-17

Monthly Report : 9 / 2017

  

   

Total/Pending/Completed Milestone - 8 / 0 / 8

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2127.512619.592619.56

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2560.1322.5602582.69

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20149/20179/2017

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3.210

Ministry Review Date

LatestLastPhysical Progress (%)Status
10-AUG-17100Completed

Monthly Status

Background Information

Project completed & commissioned.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks