Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : SYTEM STRENGTHENING OF SOUTHERN REGION - XIV.

Reported Date : 15-MAY-19

Monthly Report : 3 / 2019

  

   

Total/Pending/Completed Milestone - 10 / 2 / 8

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
297.33534.02534.02

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
400.2848.40448.68

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20140/03/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
33.30

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks