Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TR SYSTEM FOR ESTABLISHMENT OF 400/220 KV GIS SUBSTATION AT MAGARWADA IN UT DD.

Reported Date : 10-MAR-15

MOU Status : Not Under MOU for 2014-2015

Monthly Report : 1 / 2015

Cost Overrun (%)-   0

Time Overrun (Months)-    12

Total/Pending/Completed Milestone - 16 / 0 / 16

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
259.280259.28

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
148.1232.129.8210.02

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20140/01/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
52.40

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone