Reported Date :
17-APR-18
|
MOU Status :
Project Under MOU for 2016-2017
|
Monthly Report :
2
/
2018
|
Cost Overrun (%)- 260.55
|
Time Overrun (Months)-
139
|
Total/Pending/Completed Milestone -
13
/
0
/
13
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
STATUS:
Unit-I: Commissioned on 25.08.2017
Unit-II: Commissioned on 28.11.2017.
Declaration of COD for the plant is in process.
| |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |