Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NORTH EAST ELECTRIC POWER CORPORATION.
Project Name : TUIRIAL HYDRO ELECTRIC PROJECT (60MW).

Reported Date : 17-APR-18

MOU Status : Project Under MOU for 2016-2017

Monthly Report : 2 / 2018

Cost Overrun (%)-   260.55

Time Overrun (Months)-    139

Total/Pending/Completed Milestone - 13 / 0 / 13

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
368.721329.431329.43

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1184.74156.55.541341.24

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/200611/20172/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
179.720

Ministry Review Date

LatestLastPhysical Progress (%)Status
05-MAR-18100Completed

Monthly Status

Background Information

STATUS: Unit-I: Commissioned on 25.08.2017 Unit-II: Commissioned on 28.11.2017. Declaration of COD for the plant is in process.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone