Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TRANSMISSION SYS ASSOCIATED WITH KRISHNAPATNAM UMPP-PART C1.

Reported Date : 02-FEB-15

Monthly Report : 11 / 2014

  

   

Total/Pending/Completed Milestone - 19 / 0 / 19

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
324.330324.33

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
176.06035.3211.36

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20140/011/2014

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
44.70

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks