Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : WR-NR HVDC INTERCONNECTOR FOR IPP PROJECTS IN CHHATTISGARH.

Reported Date : 07-NOV-17

Monthly Report : 9 / 2017

  

   

Total/Pending/Completed Milestone - 30 / 0 / 30

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
9569.769291.039291.03

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
7078.79232.3807311.17

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20156/20179/2017

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
391.230

Ministry Review Date

LatestLastPhysical Progress (%)Status
10-AUG-17100Completed

Monthly Status

Background Information

Project completed & commissioned.