Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : NORTHERN REGION SYSTEM STRENGTHENING SCHEME-XXIV.

Reported Date : 28-MAY-18

MOU Status : Not Under MOU for 2016-2017

Monthly Report : 3 / 2018

Cost Overrun (%)-   21.9

Time Overrun (Months)-    40

Total/Pending/Completed Milestone - 10 / 0 / 10

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
723.63882.13882.13

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
702.5234.10736.62

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20145/20183/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
26.260

Ministry Review Date

LatestLastPhysical Progress (%)Status
22-DEC-17100Completed

Monthly Status

Background Information

Project completed & commissioned in March 2018.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone