Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TR. SYS. FOR PHASE-I PROJ. IN JHARKHAN AND WEST BENGAL PART-B.

Reported Date : 11-JAN-17

Monthly Report : 11 / 2016

  

   

Total/Pending/Completed Milestone - 17 / 1 / 16

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3201.4403201.44

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3273.71226.503500.21

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20140/010/2016

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1750

Ministry Review Date

LatestLastPhysical Progress (%)Status
29-NOV-16100Completed

Monthly Status

Background Information

Project completed & commissioned.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks