Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : SOLAPUR STPP.

Reported Date : 17-JUL-19

Monthly Report : 5 / 2019

  

   

Total/Pending/Completed Milestone - 39 / 0 / 39

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
9395.1809395.18

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
8617008617

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20170/05/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks