Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : VINDHYACHAL STPP STAGE-V.

Reported Date : 09-OCT-15

MOU Status : Project Under MOU for 2015-2016

Monthly Report : 8 / 2015

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 28 / 0 / 28

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3180.403180.4

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1790191612042

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20150/08/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
6590

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone