Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : NORTHERN REGION SYSTEM STRENGTHENING SCHEME-XXVI.

Reported Date : 08-JUL-15

Monthly Report : 5 / 2015

  

   

Total/Pending/Completed Milestone - 17 / 2 / 15

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
803.340803.34

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
589.893.30593.19

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20150/05/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
106.20

Ministry Review Date

LatestLastPhysical Progress (%)Status
23-SEP-14100Completed

Monthly Status

Background Information

Project completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks