Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : AUGMENTION OF TRANSFORMERS IN NORTHEN REGION - PART A.

Reported Date : 11-MAR-15

MOU Status : Not Under MOU for 2014-2015

Monthly Report : 1 / 2015

Cost Overrun (%)-   0

Time Overrun (Months)-    3

Total/Pending/Completed Milestone - 7 / 0 / 7

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
156.040156.04

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
37.5655.3092.86

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20140/01/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
55.70

Ministry Review Date

LatestLastPhysical Progress (%)Status
23-SEP-140Completed

Monthly Status

Background Information

Project completed & commissioned in Jan 15.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone