Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : COMMON TRANSMISSION SCHEME WITH ISSG PROJECTS IN NAGAPATTINAM/CUDDALOR OF TAMIL NADU - PART A1.

Reported Date : 20-MAY-15

Monthly Report : 3 / 2015

  

   

Total/Pending/Completed Milestone - 14 / 0 / 14

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
182.80182.8

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
13.931160129.93

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20140/03/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
18.779

Ministry Review Date

LatestLastPhysical Progress (%)Status
23-SEP-14100Completed

Monthly Status

Background Information

Project completed & commissioned.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks