Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NORTH EAST ELECTRIC POWER CORPORATION.
Project Name : AGARTALA GAS TURBINE PLANT COMBINED CYCLE EXTENSION PROJECT (51 MW).

Reported Date : 04-NOV-15

MOU Status : Not Under MOU for 2015-2016

Monthly Report : 9 / 2015

Cost Overrun (%)-   22.52

Time Overrun (Months)-    5

Total/Pending/Completed Milestone - 17 / 2 / 15

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
296.87363.73363.73

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
306.9611.70318.66

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20140/05/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
56.480

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone