Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : NORTHERN REGION SYSTEM STRENGHENING SCHEME - XXXII.

Reported Date : 12-MAR-18

Monthly Report : 1 / 2018

  

   

Total/Pending/Completed Milestone - 18 / 0 / 18

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
908.08969.97969.97

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
629112.630741.63

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20162/20181/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
84.50

Ministry Review Date

LatestLastPhysical Progress (%)Status
22-DEC-17100Completed

Monthly Status

Background Information

Project completed in December 2017.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks