Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : STATIC VAR COMPENSATORS (SVCS) IN NORTHERN REGION.

Reported Date : 12-MAR-18

Monthly Report : 1 / 2018

  

   

Total/Pending/Completed Milestone - 4 / 0 / 4

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
829.980829.98

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
378.644.920423.52

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/201610/20171/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
940

Ministry Review Date

LatestLastPhysical Progress (%)Status
22-DEC-17100Completed

Monthly Status

Background Information

Project completed in December 2017.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks