Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TRANSMISSION SYSTEM ASSOCIATED WITH LARA STPS-I (2X800) GEN. PROJECT OF NTPC.

Reported Date : 18-AUG-17

Monthly Report : 6 / 2017

  

   

Total/Pending/Completed Milestone - 3 / 2 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
400.470400.47

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
81.1184.10265.2

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20170/06/2017

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1600

Ministry Review Date

LatestLastPhysical Progress (%)Status
23-MAR-170Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks