Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : FGUTPP, UNCHAHAR STAGE-IV (1X500 MW).

Reported Date : 17-JUL-19

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2019

Cost Overrun (%)-   0

Time Overrun (Months)-    29

Total/Pending/Completed Milestone - 28 / 0 / 28

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3363.1203363.12

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2244002244

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20160/05/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone