Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : TANDA TPP STAGE-II (2X660 MW).

Reported Date : 06-SEP-21

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 8 / 2021

Cost Overrun (%)-   7.11

Time Overrun (Months)-    N.A.

Total/Pending/Completed Milestone - 42 / 0 / 42

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
9188.9809842.02

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
7391.78007391.78

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20190/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone