Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : DARLIPALLI STPP STAGE-I (2X800 MW).

Reported Date : 06-SEP-21

Monthly Report : 8 / 2021

  

   

Total/Pending/Completed Milestone - 42 / 0 / 42

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
12532.4413140.9113140.91

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
11803.07281.92012084.99

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20185/20217/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
501.120

Ministry Review Date

LatestLastPhysical Progress (%)Status
06-AUG-210Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks