Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : INTER-REGIONAL SYSTEM STRENGTHENING SCHEME IN WR AND NR (PART-B).

Reported Date : 03-JUL-18

Monthly Report : 4 / 2018

  

   

Total/Pending/Completed Milestone - 12 / 0 / 12

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
6517.3606517.36

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3772.8003772.8

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20180/04/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
939.50

Ministry Review Date

LatestLastPhysical Progress (%)Status
09-MAY-18100Completed

Monthly Status

Background Information

Project completed & commissioned as per schedule.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks