Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : SYSTEM STRENGTHENING IN SOUTHERN REGION - XXIII.

Reported Date : 01-OCT-21

Monthly Report : 9 / 2021

  

   

Total/Pending/Completed Milestone - 5 / 2 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
203.280260.03

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
200.1600200.16

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20170/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks