Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : INSTALLATION OF STATCOMS IN WESTERN REGION.

Reported Date : 07-FEB-19

Monthly Report : 12 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1071.241071.241071.24

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
556.9692.30649.26

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20179/201812/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
155.90

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks